.

نیروگاه سیکل ترکیبی 77 مگاواتی

این نیروگاه 77 مگاواتی شامل یک واحد گازی 44 مگاوات GE FRAME 6 و یک واحد بخار 33 مگاوات  ABB می باشد 

77MW CCGT (50HZ) Frame 6B (PG 6561B)

Frame 6 B gas turbine PG 6561B, LEC upgraded one,  converted in 2009 from Syngas to LEC natural gas combustion system


GT transmission
Generator Alstom T 214-234
GT controller system (Mark V)
Co2 fire extinguishing system of the gas turbine
Heat recovery steam generator, standard boiler Duisburg 4x4 sygas-fired additional burner
Main steam turbine, double extraction - contensation turbine
ABB Turbine Nürnberg GmbH, type VEE 40
Boiler feed water pumps 1 and 2 Sulzer Pumps Germany
Contensation steam turbine SST 060, Siemens Turbomachinery

Cooling water pumps 1 and 2 and 3 KSB AG Dt.,
Cell cooling turbine 1 and 2, GEA Energietechnik GmbH
Full desalination plant 2.9 sqm, Hager and Elsässer GmbH

this also includes:

Housing gas turbine generator set with filter house
Gas turbine machine transformer 10/30 KV; 55 MVA, Pouwels
Heat recovery steam generator with gas turbine - flue gas duct and chimney
Machine house - steel structure, isopanels
Steam turbine machine transformer 10/30 KV; 37.5 MVA
both cell coolers
Gas reducing station - without the building itself
Double girder overhead traveling crane 25 to. and 6.3 tons,
Elevator boiler house 500 ZPP, GEDA -

During the conversion of the GUD to natural gas, the following work was carried out on the main units
Gas turbine
Hot gas path inspection
Exchange of the 10 transition pieces
Exchange of the 10 burners with Wueruündrphren
Exchange of the guide u, blades of all 3 stages
Installation of a LO Nox system
Adaptation of the control to the new driving style (software change)
Transmission revision
Refilling the turbine oil

In 2010 a 3-stage air filter was installed
Gas turbine generator
pull large revision with inductor
Insulation measurements
The conversion of the GT was carried out by Ansaldo Thomassen.

Steam turbine
open the turbine
Bring runners to the factory, material tests, blasting, sheet metal, balancing
Reseal parting joint
Close withdrawals that are no longer required
Realignment of the runner
Renewal of sealing steam control
New turbine control and adaptation to the steam turbine generator control system
The same work was carried out on the generator as on the GT generator.
The revision work was carried out by Turbomaschinen (TMS).

Waste heat boiler
The AHK received a water pressure test
Comprehensive material tests were carried out
All TÜV-relevant tests including the associated containers and pipelines

 

مرجع خاص

محصولات مرتبط

محصولات برتر هفته